The Balance Corp

TBC / Resource Centre / IM03

Pilot plan with stop criteria

Before implementing, agree on how to detect risks, review evidence, and decide to continue, adapt, or stop.

Evidence and implementationProtocol + risk matrix55 approx. minNo account
Project management, innovation, and implementation managersRecord of pilot decision gates and operating protocol

Free, non-binding material. Your responses are not sent to TBC.

Before you start

A pilot program must address a specific uncertainty and establish review rules before consuming resources or exposing participants to unnecessary consequences. Process evaluation distinguishes between implementation, mechanisms, and context; focusing solely on end results can obscure why a program was implemented or failed [1].

Implementation outcomes—for example, acceptability, adoption, feasibility, and fidelity—must be distinguished from the impact on people or systems [2]. This distinction allows for proportionate decisions without turning preliminary evidence into claims of effectiveness.

Step-by-step application

  1. 1

    Defines the decision

    Ask if the pilot is looking for feasibility, adoption, technical performance, or an initial outcome signal.

  2. 2

    Establishes safeguards

    Define exclusions, responsible parties, incident protocols, authorizations, and mechanisms to stop.

  3. 3

    Defines evidence in advance

    Establishes main indicator, sources, minimum quality, comparison conditions and independent review.

  4. 4

    Prepares milestones

    Establish review schedule, maximum budget, responsible parties, and deviation recording process.

  5. 5

    Applies gates

    Upon reaching the milestone, record the decision: continue, adapt, stop, or gather more evidence; retain the justification.

Worked example: fictional scenario

Fictional example: A program trials voluntary digital care for six weeks. It stipulates that the trial will be discontinued if there is inappropriate data exposure or if alternative care cannot be guaranteed. Session completion measures service performance, not individual well-being. At the end of the trial, the team documents any issues and decides whether adjustments to the service are needed.

Technical criteria for responsible use

How to interpret this resource

The value of a pilot project lies in making a more informed decision without accepting disproportionate risks or costs. Not all pilot projects aim to measure impact; some simply seek to determine whether a process can operate under real-world conditions. Process evaluation examines implementation, mechanisms, and context—elements that explain why results can vary [1]. Therefore, it is necessary to define the nature of the uncertainty from the outset. A pilot project without stopping criteria transforms a learning experiment into a tacit obligation to continue even if risks have emerged.

Evidence needed before deciding

Indicators should include operating conditions, incidents, costs, and unforeseen effects. User acceptance, team adoption, and adherence to core components are implementation outcomes distinct from final benefits [2]. Document for each source who can access it, with what authorization, and how missing data will be handled. Do not assume that the absence of reports implies the absence of incidents. Design an alert mechanism with identifiable responsible parties and criteria for escalating the case to authorized levels. The criteria should not be adjusted retrospectively to declare success.

Facilitation and validation

Before implementation, organize a review meeting where an operations manager presents the protocol and another person challenges its assumptions in an adversarial manner. Request concrete examples of situations that would lead to halting, temporarily suspending, or modifying the test. Establish a date for an interim evaluation and specify who will verify the evidence. At each meeting, record any deviations from the original design and whether they alter the possible interpretation. The deliberation should be based on observable facts, not on pressure to justify resources already spent.

From findings to a decision

At the end of the study, consider four dimensions: sufficient implementation, preliminary indication of results, acceptable risks, and continuation costs. A pilot program may pass some dimensions but not others; don't reduce the decision to a single overall score. Continuing may involve learning with a different design, not expanding coverage. Stopping may be a responsible outcome if serious incidents, non-compliance, or a lack of essential conditions occur. When the subjects are people, especially minors or vulnerable groups, relevant institutional authorizations and reviews are prerequisites, not add-ons to be completed afterward.

Methodological quality checklist

  • Question, sample, scope, budget, and milestones are defined before execution.
  • Implementation indicators are not presented as impact evidence.
  • There is formal authority to suspend in the event of incidents and documented criteria.
  • Protocol modifications are dated and justified.
  • The final gate separates results, quality, risks, and cost before a decision is made.

Common mistakes to avoid

  • Defining success criteria only after seeing the results.
  • Failing to assign someone with authority to suspend implementation.
  • Treating serious incidents merely as reputational issues.
  • Conducting tests involving people without the required authorizations.

Scope and limitations

It does not confer ethical, administrative, or regulatory authorization. It does not replace committees, professionals, or formal safety protocols.

Foundations and references

The cited sources support methodological principles. The original TBC worksheets are not reproductions of third-party instruments.

  1. Moore, G. F. et al. (2015). Process evaluation of complex interventions: Medical Research Council guidance. BMJ, 350, h1258. Open source ↗
  2. Proctor, E. et al. (2011). Outcomes for Implementation Research: Conceptual Distinctions, Measurement Challenges, and Research Agenda. Administration and Policy in Mental Health, 38, 65–76. Open source ↗

Your draft document

Record of pilot decision gates and operating protocol

This output is an exploratory draft, not an independently validated assessment or certification.

Decision and Uncertainty

Not yet completed

Scope and Responsibilities

Not yet completed

Feasibility Indicator

Not yet completed

Outcome Indicator

Not yet completed

Risks and Controls

Not yet completed

Maximum Budget and Milestones

Not yet completed

Stopping Criteria

Not yet completed

Decision Record

Not yet completed

TBC / Next resource

Does this decision require more support?

The tool is free and self-contained. If implementation involves multiple stakeholders or constraints, TBC can support design and implementation of pilot projects.